Last week,we put windows and doors on position temporarily,then, we fixed soffit.
Put windows and doors on position temporarily with small pieces of block(3mm to 8mm).Measure window frame or door frame from inside,beyond lintel stud or sill 10mm,then nail them temporarily.For big door,we put steel and plastic mat on the sill before we fix it.
Fix soffit under soffit frame, nail one side on the nogs,other side is in fascia or fly rafter,connect them with jointer.
we also fixed cavity batten on the wall frame horizontally,under soffit directly,1 nail/300 mm.