We had had two weeks break.We have been continue erecting wall framing and we have finished it this week end.I try to write the process down.
Steps of erecting wall framing:
1.Pre nail frames are delivered on site;
2.Read the plan of frame's position;
3.Establish building line ;
4.Start with back walls;
5.connecting next wall;Generally from corner;
6.2 nails/600mm;Nail plate with galvanize nail;Flush on outside;Fix bottom temporary;Interior frames temporary connected;Leave bathroom walls free frame connection;Put temporary braces on frames(square building);Put temporary braces on floor(enforce frames);
7.Looking for connecting frame,work to the front;
8.Straightening frames; Level corners at stud's both side,top and bottom plate have to touch;
9.String line on top and bottom plate,checking with 3 blocks(exactly the same thickness);
10.Fix frame permanent except bathroom wall.